Stepnell’s Construction Update
With the recent bad weather, the works to the Town Hall have had to slow down, but general progress over the last few months has included:
The counter battening to the roofing works have completed ahead of the slate installation.
The lift shaft is complete awaiting bracing detailing
The steel frame to the extension area delivered on 5th January 2026
The steel plates have been installed and amendments made to enable the Steel Framing System to commence
Steel Framing System recommenced to the 1970’s building on 19th January 2026
The Internal lime rendering is ongoing (with the exception of the reveals, that will be completed after the main walls) this means around 90% is complete.
Quoins / stonework are being formed around existing openings
The lead work has been prepared and laid to the Town Hall valleys.
Reinforcement for the roof man-safe-system has been fitted
The lifting beam and lid to the lift shaft have been installed.
The masonry to the north and south elevations of the 1970’s building is on-going ahead of the Steel Framing System and window installation.